Celepsa confirms completion of the Second Capillucas Dam Maintenance 2018

CelepsaCelepsa

Tuesday, March 20th, 2018- Celepsa confirmed that the Capillucas Dam’s Second Maintenance Activity 2018 finished yesterday, Monday, March 19th at 15:12 hours. Given the natural flooding of the Cañete River this morning, Tuesday, March 20nd, it is thought appropriate to share the detailed flow data during and after the Capillucas Dam’s Second Maintenance Operation 2018:

Day Time Flow rate
Putinza
(m3/s)
Flow rate
Socsi
(m3/s)
Observations
19/03 05:00 150   05:14 START OF MAINTENANCE – Opening of Capillucas floodgates
19/03 06:00 142  168  
19/03 07:00 140    
19/03 08:00 165    
19/03 09:00 163   Start – Capillucas dam sediment flushing
19/03 10:00 160    
19/03 11:00 154    
19/03 12:00 150  182  
19/03 13:00 145    
19/03 14:00 142    
19/03 15:00 140    15:12 END OF MAINTENANCE – start of filling Capillucas
19/03 16:00 138    15:30 Start of sediment passage through Socsi
19/03 17:00 138    
19/03 18:00 148  158  
19/03 19:00 160    19:30 Arrival of sediments at Boca de Río
19/03 20:00 163    
19/03 21:00 165    21.30 End of sediment passing through Socsi
19/03 22:00 170    
19/03 23:00 175    
20/03 00:00 178    
20/03 01:00 206    
20/03 02:00 198    01:30 End of sediment passage at Boca de Río
20/03 03:00 189    
20/03 04:00 180    
20/03 05:00 178    
20/03 06:00 171  230  
20/03 07:00 170    
20/03 08:00      

According to the data, the maintenance operation on this occasion began at 05:14 hours and ended at 15:12 hours yesterday, Monday, March 19th; the sediment transport from Capillucas to Socsi concluded at 21:30 hours the same day.

Similarly, the information supplied indicates that the increase in Cañete river flow recorded early this morning in Socsi began hours after the gates were closed and maintenance of the Capillucas Dam was finished. As a result, this river flooding is caused by the activation of streams in the middle basin during the rainy season and has nothing to do with Capillucas Dam maintenance.

As usual, Celepsa keeps the flow record with date and time in the middle zone available at the following link: https://a.celepsa.com/users/riocanete/

Finally, the organization expresses its readiness to collaborate, communicate, and provide clear information.